Two
parallel but quasi independent Block Programs, one for the load
and the other for the temperature, define Thermo-Mechanical Cycling.
Each block may consists of several stages. In the case of temperature
block, each stage is defined by starting and finishing times and
corresponding temperatures. In the case of load block, each stage
can be either ramp - hold or cyclic. Although each stage of the
block programme for load and temperature can be set independent
of each other, provision is made to compel load to wait for the
temperature to be within a given tolerance band. The combined block
can be repeated as many times as required or until any one of a
number of "target" end of test criteria is met. While
the combined temperature / load stages are in progress DCPD readings
will be carried out at regular intervals.
|
|
|
|